Restoration Update August 2016

John Oxley is a 1927 Clyde built steamship being restored to operating condition by Sydney Heritage Fleet at Rozelle Bay in Sydney. The restoration is advanced with hull basically complete – Current work continues on replacement of her steel main deck while engineers work on machinery, piping, skin fittings and propeller shaft repairs.

John Oxley in 1970 steaming proudly into Sydney Harbour after delivery voyage from Brisbane.

Recent Work

Naval Architect

John Butler Designs (as project naval architect) advise that the weight of the finished John Oxley will be 706 tonnes. The planning team have systematically listed the weights and locations of all steelwork, timberwork, fittings and equipment onboard a finished John Oxley. The naval architect has transferred these to the 3D CAD stability model for our vintage steamship. From this, they have approved the design weights of forward hold and main hold tween decks plus sewerage tanks, gen sets and associated equipment. Decisions made by the naval architect here have allowed our fabricators to commence work in these spaces.

Boat Deck

Rainwater from leaking through the boat deck causes much deterioration on ships like John Oxley, hence the hard decision was made to steel plate in this deck. Our naval architect advised that the extra weight was acceptable within the stability model and work commenced. The old wooden deck was removed and steel deck plates have now been fastened down and seal welded. A future composite wooden deck is planned, but for now the lower compartments are free of rain water and dry. A great result and thanks to our fabrication team here.

Volunteer drafter Glenn has prepared detailed plans of this deck which fix locations of the various fittings such as aft mast step, boat chocks and davits, vent cowls, life jacket boxes, Carley floats and railing positions. Shipwrights are preparing to install boat deck fittings.

A substantial scaffolding system around the boat deck perimeter was designed and signed off by Scaffold Training Australia. It will be removed when the boat deck stanchions and railings are returned. Thanks to STA for their help here.

Main Deck

The fabrication team under Steve has returned to work on the starboard side main deck over the boiler space and are continuing new steel deck here. Old rusted and poorly repaired steel deck is first cut away and new steel installed. New steel plates here are supplied blasted and coated with Zinc primers. Some repairs to deck beams are needed, but these are minimal. This work takes place Tuesday to Saturday and we seriously need additional workers.

Workshop Activity

Shore workshop team are producing a range of projects for parts on John Oxley. Included are bunker and well deck hatches for later fitting.

An interesting project has been the smithing of traditional brackets for hatch tarpaulin wedges. These were cut from plate and formed to shape under our old 50 tonne press. Holes were drilled and a dip in the galvanising tank followed.

Forward Hold

Work has commenced in the forward hold on a permanent safe work platform and on the forward firepump stand. Work is well advanced here as shown.

Engine Room

The work team under Garry Burns has achieved much this year. Highlights have included construction, galvanising and install of the bilge suction system in galvanised steel.

Auxiliary machinery is installed and is being connected to services. The engine room crane beam and runner is restored and back in place. Another milestone was the completion of engine room condenser system skin fittings. The original cast iron sea valves were condemned and RMS surveyors mandated modern sea valves as shown. Size is 10”

Cleaning down the main engine has commenced and most auxiliary machinery will be running on compressed air by years end.

Work continues on cleaning the propeller shaft within the tunnel and cleaning and servicing the intermediate shaft bearings. Work has commenced on servicing/replacing oil lines to the sterntube.

Suitable WH&S is already being discussed as to how to enable the engine room to be opened to the public for tours.

Electrical

Design planning by Grant Campbell continues throughout the ship to provide for a complex array of requirements. The electricians already work on supplying construction wiring for lighting and power to the restoration. New cable trays are installed above in the engine room and a new cable tray system to run along the port side machinery spaces has commenced. This will carry power from the gen set to various parts of the ship.

Our People

Unfortunately our lead fabricator Onzie Ratu was on light duties due to health issues, but has found it necessary to retire from the project. We therefore have an immediate need for additional metal fabricators. So if you are a fabricator and have time on your hands, we certainly need you.

The team also needs descalers, painters, general workers and potential ironworkers.